"Spring School 2005: Benefits Management"
Event Report
The Spring School this year was on that often neglected area of projects – benefits management.
Over 50 attendees took a look at this subject over four weeks with speakers from varied backgrounds.
Jim Stockwell, of Denmans Assignments Limited, began the series with a presentation on The Business Case –
Its Purpose and Preparation. Jim began by reminding us that the Government’s Gateway Review process
identified that business case review resulted in a higher level of “red” flags than in any other
areas of the project lifecycle. Few projects have robust benefits management processes and most
projects fail to deliver anticipated benefits. The business case should be developed and approved
in distinct phases: from outline through to full business case. It should then be carefully updated
with changes caused throughout the lifetime of the project. It should look at strategic fit and
options appraisal (including value for money and risks), not just for savings or increases in
performance, but should also assess achievability, affordability and whether the benefits can be measured.
Jim quoted a number of interesting examples to illustrate where poor assumptions or weakly developed new
processes and lack of wide consultation could undermine the business case. One example was the
NHS “choose and book” programme allowing patients some choice on hospital, consultant and first
appointment time. Despite being an interesting concept, the extra time GPs would need to
process the booking had not been fully accounted for and extra funding was needed for
implementation. A lively debate followed and it was generally acknowledged that more
rigour applied to the business case would result in exposing risks and issues earlier
and enable them to be tackled before they seriously impacted on the programme.
Jon Bassett, Director of Implementation and Lize Dupe, Head of Benefits realisation of AXA Life
set the scene in their presentation by explaining that 25% of management time was involved in
managing change and that it was essential for a structured model to ensure each new programme
flowed through from the original vision, through detailed planning linked to key performance
indicators(KPIs) in order to guarantee realisation of planned benefits. Most big programmes
of change were introduced on the basis of achieving benefits over their product life of
possibly up to 20 years. (Different to many organisation who had to achieve payback on
projects within 2-3 years) They explained how important it was that senior sponsors are
fully involved in writing the business case as part of taking full responsibility for ensuring
projects were successful. Their own performance targets are drawn up to reflect achievement of
the proposed benefits. To deliver this requires a “measurement culture” to ensure processes are
fully in place during project implementation to enable the accurate monitoring of KPIs. Because
the delivery period of about 2 years is considerably less than the realisation period of up to
20 years, managers’ priorities are weighted higher on realisation than delivery.
The third lecture on Benefits Centred Project Management featured David Wilkin of MMP Consulting
and Steve Money. David began by emphasising the need to be thinking about project
benefits at all times. This improves the way projects are organised and reduces the risk
of any adverse effects on the business. The key to this approach is the structuring of a
project into work package milestones linked to implementing elements that deliver complete
sets of benefits rather than implementing convenient tranches of technology. (e.g. a partially
complete infrastructure with high priority functionality on it that works and delivers benefit,
rather than a full infrastructure with nothing on it yet) Hand in hand with these priorities is
the need for a commitment from management to co-operate between all stakeholders, the need for
a benefits realisation management role, the prioritising of functionality between must haves,
should haves and could haves (MOSCO), and a plan which sets out the phasing of what benefits
are being delivered over the life of the project – as well as the delivery of the technical
work packages. Steve then outlined three interesting case studies which illustrated the concepts outlined.
The fourth and final lecture was delivered by Ian Kennon, a programme manager with IBM
on the topic Benefits Management - Post Implementation and Monitoring. He recounted some
of his experiences in three large programmes. On the RAF Logistics renewal programme known
as LITS in which pre-determined savings in parts and maintenance costs were built into
future departmental budgets before the programme was completed. So, when the programme
was delayed and de-scoped, the benefits profile changed and required budgets to
be re-profiled. The second was an agreement for the global outsourcing of IT with a
large pharmaceutical company, which resulted in a benefit realisation model being built
into the contract - so that the pharmaceutical company maintained the service level
required and at the same time IBM delivered cost savings in order to meet its own
profit targets. The final example was the consolidation of disparate systems and
processes for a mobile telephone company. The overall objectives being to enable
increase in market share through flexibity and speed to market of new products and
services and a relative reduction in IT spend.
The series of presentations were very well received and we are hoping to repeat this School
in the autumn at another venue, over 4 weeks during October 2005.
Our sincere thanks must be extended to IBM UK for the high level of hospitality at their
Southbank facility over the four evenings.
|